Anatomy of a developer insolvency: five red flags that were visible beforehand (2026)
First things first: insolvencies announce themselves structurally
After every major insolvency the same story follows: nobody saw it coming, interest rates rose too fast, the market turned too abruptly. That is true for the trigger and misleading for the cause. A rising interest rate only brings a company down if its structure cannot withstand it, and as a rule that could be checked beforehand.
Since 2023 several large developers in Germany have filed for insolvency, including Gerchgroup, Euroboden, Project Immobilien and the Düsseldorf companies Centrum and Development Partner 12. At Gerchgroup alone, a project volume of around four billion euros was affected 13.
The trigger: interest rates and construction costs at the same time
Observers consistently name high financing and construction costs, energy requirements and regulatory uncertainty as the bundle of causes 18. The most effective single factor was the interest rate: the European Central Bank raised its key rate very sharply within a short time 46.
What matters is that it happened at the same time. Rising construction costs alone can be passed on through the sales price as long as demand holds. Rising interest rates alone can be cushioned by a longer holding period as long as the calculation has headroom. Both together close both escape routes at once, and hardly any model was designed for that.
Red flag 1: the structure is not legible
The Signa case is the largest documented example. According to the analysis by the Momentum Institut, Signa Holding had total assets of around five billion euros but was classed under company law as a small GmbH, with the result that there was no audit obligation for the annual accounts and no supervisory board 45. The group’s liabilities stood at around EUR 8.6 billion, with more than 300 creditors affected 7.
- The question this tests: Who is your counterparty, who owns it, and who is liable beyond that?
- The warning sign: An organisation chart that only arrives on request and then looks different from the first time.
- The hard test: Ask for the last two annual accounts of the counterparty, not those of the group.
- The honest downside: A lean structure is not yet a healthy one. Legibility is a necessary, not a sufficient condition.
Red flag 2: growth through acquisitions instead of completions
Project development is a business with long lead times. Anyone who acquires faster than they complete builds a pipeline that looks good at first and consists entirely of interim financing. As long as the market rises, that is leverage. As soon as it stalls, it is a running cost item with no counter-value.
- Ask for the ratio of acquisitions to handovers over the last three years. Not project volume, but completed units.
- Ask about the average holding period of plots on which construction has not started. Over 24 months without a construction start needs a justification.
- Have the interim financing costs of the pipeline quantified. Every solid developer knows this figure by heart.
- Check whether sales to affiliated companies are counted as completions.
Red flag 3: valuations replace transactions
In a liquid market the sale confirms the valuation. In an illiquid market the valuation replaces the sale, and that is the point where balance sheets and reality drift apart. From a risk management perspective the Signa case is traced back to exactly this: a model that depended on continuously rising values and a continuously available supply of fresh capital 6.
Red flag 4: the interest stress was never calculated
This is the point where calculations can be checked fastest, and the one that is missing most often. The assumptions are stated openly here: total investment costs of EUR 20 million, 80 percent debt, 24 months of construction.
If a construction overrun of six months is added, the picture shifts markedly once more. That is exactly why every set of documents should contain a scenario with a higher interest rate, a later sale and a lower price, and if it is missing, that is the most telling piece of information in the whole folder.
Red flag 5: divisions with different cycles are tied together
At Signa, the close interlinking of retail and real estate is described in the Momentum Institut’s analysis as the structural defect that ultimately led the holding into insolvency 45. The pattern is transferable: when one division supports the other, both interlock at the same time in a downturn.
| Observation | Harmless explanation | Dangerous explanation | What you request |
|---|---|---|---|
| Many companies | Project companies per project, market standard | Risk shifting and lack of transparency | Organisation chart plus list of holdings |
| Growing pipeline | Countercyclical acquisition | Interim financing without completion | Acquisitions against handovers, 3 years |
| High valuations | Location development | Missing transaction evidence | Last three comparable transactions |
| No interest scenarios | Fixed rate in place | Calculation does not carry stress | Sensitivity of interest rate, construction time, price |
| Cross-subsidies | Internal liquidity balancing | One division finances the other | Cash flow statement per division |
Where the market stands in 2026
The clean-up is not over. In 2025, 24,064 company insolvencies were filed in Germany, 10.3 percent more than the year before; with 104 cases per 10,000 companies, construction was among the three most affected sectors 9. In the first half of 2026 the figures in construction rose by a further 4.5 percent, and Creditreform expects stabilisation in 2027 at the earliest 10.
For due diligence this means: the probability of meeting a weakened counterparty is higher than in the years in which today’s review routines emerged. What belongs in a complete review is set out in the due diligence checklist for developer projects.
The checklist before the capital commitment
- Identify the counterparty, not the group, with annual accounts, shareholdings and liability position.
- Have acquisitions set against completions over the last three years.
- Have valuations backed with transactions: at least three comparable cases, ideally with independent parties.
- Demand a stress scenario: interest rate plus 300 basis points, construction time plus six months, sale price minus five percent, all at the same time.
- Ask about cross-subsidies between divisions and companies, including a cash flow statement.
- Fix your own ranking and the collateral in writing before money flows. Afterwards it is no longer negotiable.
The right question is therefore not: is this company sound? But: what would have to happen for it to no longer be, and how far is that state from today?
Frequently asked questions
Sources
- [1]WirtschaftsWoche: After Centrum, Project Immobilien and Euroboden: Gerchgroup files for insolvency https://www.wiwo.de/unternehmen/dienstleister/nach-centrum-project-immobilien-und-euroboden-immobilienentwickler-gerchgroup-meldet-insolvenz-an/29348518.html
- [2]Börsen-Zeitung: Project developer Gerch is insolvent https://www.boersen-zeitung.de/unternehmen-branchen/projektentwickler-gerch-ist-insolvent
- [3]Cicero: Gerch insolvent: next collapse among real estate developers https://www.cicero.de/Wirtschaft/gerch-immobilien
- [4]Momentum Institut: Benko and Signa: causes and consequences of the record insolvency https://www.momentum-institut.at/publikation/benko-und-signa-ursachen-und-folgen-der-rekordpleite/
- [5]Momentum Institut: On the Signa case: causes and consequences of the record insolvency (PDF) https://www.momentum-institut.at/wp-content/uploads/2024/05/in-sachen-signa-ursachen-und-folgen-der-rekordpleite-momentum-institut.pdf
- [6]Controller Institut: The SIGNA case from the perspective of risk management and controlling https://insights.controller-institut.at/der-fall-signa-aus-sicht-des-risikomanagements-und-controllings/
- [7]CERHA HEMPEL: The decision of the Vienna Higher Regional Court on the insolvency of SIGNA Prime Selection AG https://www.cerhahempel.com/blog/real-estate-insider/the-decision-of-the-vienna-higher-regional-court-on-the-insolvency-of-signa-prime-selection-ag-an-analysis
- [8]Haufe: Lull among project developers: new cyclical high only in 2029 https://www.haufe.de/immobilien/investment/immobilienprojektentwicklung-service-development-ist-im-trend_256_551962.html
- [9]Federal Statistical Office: Company insolvencies in 2025: +10.3 % on the previous year https://www.destatis.de/DE/Presse/Pressemitteilungen/2026/03/PD26_085_52411.html
- [10]Creditreform: Insolvencies in Germany, first half of 2026 https://www.creditreform.de/aktuelles-wissen/pressemeldungen-fachbeitraege/news-details/show/insolvenzen-in-deutschland-1-halbjahr-2026
- [11]§ 15a InsO: Duty to file for insolvency for legal entities https://www.gesetze-im-internet.de/inso/__15a.html